Skip to main content

Rider's Almanac Blog

From the GM METRO Green Line Minneapolis Safety St. Paul Transit Improvements

Green Line progress on track

| Wednesday, September 11, 2013 2:00:00 PM

From Brian Lamb, Metro Transit General Manager

The Minnesota State Fair is over but our planning for next year’s event is already underway. One of the most changes we’re preparing for: light-rail connections from the METRO Green Line.

The Green Line’s role in next year’s State Fair service is just one example of the myriad ways transportation in the Twin Cities will change when the region’s second light rail line begins operating.

We’re getting closer to that new reality with every passing day, too. Green Line construction is 96 percent complete and testing is well underway. Light-rail vehicles have been towed the full length of the new track and trains have run on energized segments of the line through the University of Minnesota campus.

Here’s a snapshot of where the project stands today:

> Infrastructure: In August, ground was broken for an enclosed connection that will provide access between the Central Station and skyway system in downtown St. Paul. Over the next several months, more overhead wire and equipment will be installed and ticket machines, NexTrip display signs and security cameras will begin appearing at station areas. Staff will be at Sunday’s St. Paul Open Streets event to provide tours and answer additional questions about these station areas.

> Vehicles: To date, we’ve received nearly half of the 59 new type II Siemens light-rail cars that will be used on the Green and Blue lines. Twenty of these light-rail vehicles have already been put into service on the Blue Line while more are being tested and certified each week. Support vehicles will also be required to maintain and operate the line. In October, we expect to receive a new vacuum truck that will be used for clearing street-embedded track on the Green and Blue lines. Equipment that will be used for snow clearance and overhead line maintenance is also arriving.

> Outreach: A public safety campaign that urges pedestrians and motorists to be aware around stations and construction ares was rolled out earlier this year. As testing activities accelerate, we will focus the campaign more heavily on safety around trains themselves and continuing to share this message with schools and other groups located on and near the line. 

> Service: More trips on several connecting bus routes were added in late August, giving customers an early opportunity to become acquainted with the new bus schedules over the months ahead. It’s expected that more than one-third of Green Line rides will be transfers from buses. A comprehensive plan for optimizing bus service in the Central Corridor area was completed last year. 

> Personnel: About half of the 176 new jobs – from rail supervisors to technicians to track maintainers and helpers – have been filled. Nine Green Line train operators have begun training and by the end of the year the majority of the 61 new operators will have moved over from our bus operations division.   

In both obvious and subtle ways, the METRO Green Line will change the fabric of the Twin Cities. We at Metro Transit hope you’re looking forward to it as much as we are.