Penn Avenue Improvements Project Planned Detours
Detours may be adjusted during construction. View detour map for active detours.
All truck and through traffic directed to Lyndale Ave. for all construction segments. Some parking may be restricted on local and bus detour routes. Temporary bus stops will be set up along bus detour routes.
Penn & Plymouth Segment - Construction on Penn between 12th Ave and 14th Ave
Local traffic and bus detours run northbound on Queen Ave, southbound on Russell Ave. Major construction complete.
Penn & Golden Valley Road Segment - Construction on Penn between 17th Ave and 21st Ave
Local traffic detours run north on Queen Ave, southbound on Russell Ave. Major construction complete.
Penn & West Broadway Segment - Construction on Penn between 23rd Ave and 26th Ave
Local traffic will be detoured to West Broadway Ave and Logan Ave.
Bus traffic detours run northbound on Thomas Ave, southbound on Sheridan Ave.
Construction began June 18. Duration of up to 6 months.
26th to Lowry Reconstruction Segment - Construction on Penn between 26th Ave and Lowry Ave
Local traffic and bus detours run on Queen Ave. Construction began April 9. Duration of up to 6 months.
Penn & 36th-Dowling Segment - Construction on Penn between 35th Ave and 39th Ave
Local traffic and bus detours run on Queen Ave. Duration of up to 2 months.
Penn & 43rd Segment - Construction on Penn between 42nd Ave and 44th Ave
Local traffic and bus detours run on Oliver Ave. Duration of up to 2 months.