
Work on the Selby Avenue resurfacing project continues on schedule as crews advance pavement improvements along the corridor.
Selby Avenue is open to vehicles and transit. Transit customers are encouraged to monitor Rider Alerts for the most up-to-date information about B Line and Route 72 service. Motorists are encouraged to follow any detour signage in place around the project area.
Completed work
Crews have completed paving operations on Selby. Temporary striping has been installed from Snelling Avenue to Lexington Parkway to help guide vehicles safely through the project area until striping is completed in a few weeks.
Upcoming work
Temporary striping was completed between Lexington Parkway and Dale Street the week of May 18. Permanent striping will be completed after the new pavement has had time to cure, which is expected to take roughly two weeks. Parking will be restricted on Selby Avenue between Lexington Parkway and Dale Street for 2 to 3 nights to allow work to be completed.
Construction impacts
Residents, businesses, and travelers should expect ongoing construction impacts during work activities, including noise, dust, vibration, and the presence of heavy equipment and construction crews. Temporary traffic control, lane shifts, and parking restrictions will be put in place as needed to complete permanent striping work.